Wholesale Water Frequently Asked Questions:
What is the timeline for wholesale water from Citizens and how much water, in million gallons per day (MGD), is approved for each phase?:
- Phase 1 – Up to 2 MGD total – Operational on 1/1/2027
- Phase 2 – Up to 10 MGD total – Operational on 1/1/2028
- Phase 3 – Up to 25 MGD total – Operational on 1/1/2031
Where will Citizens Energy Group source the water supplied to send to Lebanon?
Citizens Energy Group has announced that they are bringing treated water from multiple facilities. For information pertaining to the Citizens Energy Group portion of this project, please visit CLWSP
For additional information from Citizens Energy Group on the Water Supply Program, please visit their Myths vs. Facts page. This can be found the following link. CLWSP_Myths_vs_Facts_April 2026.pdf