Projects

Water –

Syracuse Dr. Water Main – Update 3/8/2021 This project has started.  Please be aware that there could be detours and road closures during the project. We are replacing approximately 3800 feet of 6” water main on Syracuse Dr. in the Northfield Housing Edition.

Williams St. Bridge Water main reroute – This project will reroute the water main that goes through the deck of the bridge on Williams St.  Projected start date 3/27/2021

Elm St. Water Tower Painting – This project will provide new paint for the Elm St. Water Tower.  Projected start date 8/1/2021

 

 

 

Wastewater –

Sewer Lining Project – Area of Fordice St., Park St. and Busby St.  Currently on-going

Ulen Countryside Lift Station Pump Replacement – This project will replace the pump in the Ulen Countryside Lift Station.  Projected start date – 3/1/2021